October 8 Main floor showing most seating removed
October 10 Main Floor showing all main floor seating removed
October 15 showing main floor and balcony seating and stage extension removed
October 22 showing the 1925 gym as work is started on the ceiling under the auditorium stage
October 31 auditorium ceiling after asbestos removal
November 19 Wrestling Room site work
November 19 Wrestling room footings
November 19 Wrestling room walls erected
November 29 Auditorim HVAC installation and firring strips on walls
November 29 Drama makeup room started on SE second floor
December 5 Exterior view of the wrestling room construction
December 5 Interior view of the wrestling room floor cement work
December 27 Auditorium drywall progress
December 27 Auditorium sound room framing between Auditorium front doors
December 27 Ramp construction to Auditorium entrance doors
January 3 Handicapped flooring poured in balcony
January 23 Auditorium Soundbooth with sheetrock
January 28 Dressing rooms in SE corner of second floor
January 28 New stairs leading from backstage to second floor hallway by elevators
February 6 Auditorium ceiling completely removed exposing the new ductwork
February 20 Painted wrestling room seen from hallway entry doors
February 20 Wrestling room storage and bleacher area
March 22 Old gym windows being removed
March 22 Steel structure in old gym preparing for under stage workroom
April 5 Steel structure preparing for stage extension
April 5 Auditorium painting started
April 9 Wrestling room mat underlayment